METHOD STATEMENT FOR METAL
DUCTWORK- LOW PRESSURE
METHOD OF STATEMENT PART 1 FOR METAL DUCTWORK- LOW PRESSURE
C. ABBREIONS 4
D.1 International Codes…………………………………………………..…………….…4
D.2Project Specification………………………………………………….…………….…4
E.1 Project Manager………………………………………………..……………………… 4
E.2 Site Engineer …………………………………………………………………………4-5
E.3 QC Supervisor …………………………………………………………….……………5
E.4The QC Inspector …………………………………………………………….…………6
E.5The Safety Engineer/Inspector …………………………………………………………6
E.6The Site Supervisor/Foreman ………………………………………..…………………6
METHOD OF STATEMENT PART 1 FOR METAL DUCTWORK- LOW PRESSURE
A. Purpose
The purpose of this method statement is to describe the quality control procedure to be followed During installation of Metal Ductwork- Low Pressure at Dhahran Residential Community project and to detail the instructions to be followed and the documentation to be employed in order to ensure that safe installation is executed in accordance with the project specifications and standards.
B. Scope of work
The scope of this method statement is to define all activities and requirements necessary for Metal Ductwork- Low Pressure, Heating, Ventilation and Air Conditioning (HVAC) System at project in and to ensure that all works/activities, acceptance criteria, IFC drawings, specifications codes community project and to ensure that all works/activities are in full compliance with project specifications, drawings and Hvacmep standards related to installations standards, verifying
Documents comply with Hvacmep Typical Inspection Plan (TIP) related to installations.
C. Abbreviations
MS | : | Method Statement |
IC | : | Inspection Checklist |
TR | : | Test Report |
TIP | : | Typical Inspection Plan |
HVACMEP | : | Engineering Standards |
RFI | : | Request for Inspection |
PID | : | Project Inspection Department |
PMT | : | Project Management Team |
ITP | : | Inspection & Test Plan |
NCR | : | Non Conformance Report |
PM | : | Project Manager |
CM | : | Construction Manager |
PPE | : | Personal Protective Equipment |
QA/QC | : | Quality Assurance/Quality Control METHOD OF STATEMENT PART 1 FOR METAL DUCTWORK- LOW PRESSURE |
D.1 International Codes
§ | ASHRAE Handbooks | HVAC Applications, Systems and | |
| | Equipment, Fundamentals and Refrigeration | |
§ | SMACNA 1975 | Accepted Industry Practice for Industrial | |
§ | SMACNA 1981 | HVAC Duct System Design |
§ | SMACNA 1985 | HVAC Duct Construction Standard, Metal and |
|
| Flexible |
§ | SMACNA 1985 | HVAC Air Duct Leakage Test Manual |
§ | IMC | International Mechanical Code |
§ | IRC | International Residential Code |
METHOD OF STATEMENT PART 1 FOR METAL DUCTWORK- LOW PRESSURE | ||
| D.2 ProjectSpecification | |
| § SK-SPC 002 | SECTION 15891 - METAL DUCTWORK – LOW PRESSURE |
§ HVACMEP-K-001 Heating, Ventilating and Air-Conditioning
§ HVACMEP-K-100 Hvacmep Mechanical (HVAC) Code
E. . Responsibilities
E.1 Project Manager
§ To ensure that all preparation and application works are carried out according to
That contact specifications, method statement, Hvacmep Engineering Specification and manufacturer data sheet. § To ensure that the progressing of work is carried out according to the planned program and as per the approved Method Statement
§ To ensure that all the manpower, equipment and materials required to execute the Work are available
§To ensure that all related quality procedures are practiced and implemented
§To ensure that all safety matters related to this procedure are being observed
E.2 Site Engineer
§Coordinate all the site activities in accordance with approved IFC & Shop drawings, project specification and approved method statement and Hvacmep Engineering Standards.
§To provide all necessary information and distribute responsibilities to his team
To monitor the progress of work in relation with work program and to report to the PM
§To ensure that the installer is well trained for this type of work
§ To coordinate with safety officer and to ensure that the works are carried out in safe practicing method
§Site engineer shall inform mechanical Quality Control Inspector for internal inspection to check work has been done accordance to IFC & Shop Drawings, Hvacmep standards prior to preparing internal RFI for inspection and the time schedule
E.3QC Supervisor
§ Guide the QC Inspectors and monitor their performance at the site
§ Provide his subordinates with latest approved procedures, material submittals and shop Drawings.
§ Shall maintain proper filing for reports, RFI and NCRs
§ Maintain records of quality control check sheets/ reports for site tests and inspections.
§ Coordinate with SAPMT representative the required witnessing of inspection and tests.
§ Carry out surveillance so as to ensure that personal are working in accordance with approved method statement.
§ Assurances of approved methods are being used for testing and material recipient inspection.
§ Verification of material approval and vendor clarification.
E.4 The QC Inspector
§ To ensure full compliance of the work with the related approved method statement
§ Responsible to ensure that the correct, approved sizes, dimensions.
§ Ensure that IFC drawings, Shop drawings displayed on site during installation inspection.
§ Ensure that the materials being delivered to site and used are in accordance with
the project specifications and approved material submittal and material receiving RFI.
§ Shall be responsible for the inspection, preparation of RFI all documents and compiling them for the inclusion in the final documentation packaged.
To maintain comprehensive inspection and test records for the purpose of
§ reference and documentation.
§ Ensure arrangement and location of latest released for construction drawings, and specifications.
· Ensure that tools/ equipment used for testing and commissioning purpose is calibrated and certificates available. (Certificate of calibration tool will be provided during inspection time separately).
E.5 The Safety Manager / Inspector
§Ensure that the work is performed under the safety measures of the approved HSE plan
§Prior to the commencement of any activities, work force will receive Tool Box on the project safety requirement .This tool box talk will include both activity issues as well as general safety requirements.
§To maintain continuous inspections of the site activities, advise and train the involved personnel on daily basis to prevent accidents, personal injury or Property damage.
E.6 The Site Supervisor/Foreman
§ Shall have the knowledge of installation of all Ducting system in order to explain the method statement to his subordinates.
§To ensure that work is carried out properly and according to manufacturer recommendations and instructions received from the site engineer To ensure that tools, labor and materials are available
F. Safety
§Prior to the commencement of any activities the work force will receive Tool box Talk on the project safety requirements. This tools box talk will include both activity issues as well as general safety requirements
§ Direct supervisor will ensure that Protection Equipment’s, PPE, are used by site personnel at all times during this activity
§ Ensures that all scaffolding required for inspection access is in place and correctly tagged
§No personnel working on top standing on the scaffolding platform landing while pushing the scaffolding from the location to another
§ Coordinate fully with the safety officer in order to maintain safe working Condition and proper housekeeping of the site.
§All equipment and accessories have been certified for their capacity and integrity.
§ Safety and risk assessment shall be performed for every job or task, which has the potential for harm.
§All personal are issued with personal protection equipment.